Establishing the Base
Casting the anchor legs and assembling a greenhouse base.
Greenhouse on a Foundation
To achieve the best end result, it is crucial to assemble the foundation with great care.
Watch the video and learn how to best assemble and adjust the foundation for your greenhouse.
Alternatively, you can follow the written guide below.
Step 1
Readying the Area
Start by preparing the area where the greenhouse will be erected. Make sure the area is cleared, even and levelled off.
Step 2
Check the Base
The base comes wrapped in clear plastic film. Check carefully for any damage.
Step 3
Check the Model and Size
The base is labelled with the model name and size. Make sure that you have received the base you ordered.
Step 4
Check the Base Dimensions
Make sure that the base dimensions are correct before assembling and casting it in place.The dimensions are found in the assembly instructions.
Step 5
Assemble the Base
Assemble the base with the included anchor legs.
For bases bigger than 9 m2, additional anchor legs must be attached to the inner surface of the side sections (using the long bolts).
Step 6
Position the Base
Lay out the base components on the area where you plan to erect the greenhouse.
Step 7
Take Diagonal Measurements
Measure the base diagonally to square it. The two diagonal measurements must be equal.
Step 8
Mark Out the Corners
Insert a stick in the ground for each anchor leg so you know exactly where to dig/bore. Then remove the base frame.
Step 9
Bore/dig Holes
Dig or bore holes at the spots where you are going to cast anchor legs. The holes must be dug down to frost-free depth.
Step 10
Bend the Anchor Leg
Before inserting the anchor leg into the ground, bend the end to give it a better grip when cast in cement.
Step 11
Ensure that the Base is Level and Double-check Diagonal Measurements
Level off the base and re-measure it diagonally to make sure it is square.
Do this very carefully because otherwise it will be difficult to assemble and glaze (with glass or polycarbonate) if these measurements are not correct.
Step 12
Pour Cement in the Holes and Let it Set
Pour cement by the anchor leg and let it set for 24 hours or so.
Add just the right amount of water to the cement mixture. The less you add, the stronger the cement.
JULIANA GROUP
Juliana Group is a leading global supplier of quality residential greenhouses. Founded in 1963 by Mogens A. Stærmose in Odense, Denmark, the family-owned company is today run by third generation, Nikolaj Stærmose. Headquarter and production remains Odense-based with subsidiaries in the UK and Germany and export to more than 20 countries.
’We help people grow’. That is why our brands Halls, Juliana, and Gabriel Ash all set the frame for experiences that are as natural as they are magical. Despite our long history, we’re future-focused and curious on how we can improve the sustainability of our greenhouses. Learn more about Juliana and join our online community of greenhouse enthusiasts: GreenhouseForum.com